On March 28, 2007, volunteers met at Access 24 to inventory trail work needs from Access 24 to Jack Rabbit Bend.  Dave and Evelyn Thompson brought their Kawasaki Mule for volunteers to ride in.  The route was GPS'd by Sue and Dave for a total of 4.2 miles.

While in route, Dave cut a tree off the trail, and used it to fill a very bad rut just north of the northern waterfall.  We cut a new path around the rut.  On the northernmoist tip of this section of trail, the shoreline trail was moved to an old roadbed to avoid a boggy area.  The new section of trail passes between two scenic rows of big trees.  Trash was picked up from the trail as we went.

Daves Mule lost power as we were returning to the parking area.  Volunteers made it safely back, loaded up the Mule and continued on foot from Jack Rabbit Bend. 

At Jack Rabbit Bend the new toilet area was observed, and Dig-rite markings were checked.  Lunch was eaten at the picnic table, before checking the final loop of the trail on foot.

Maps were marked up with other needed improvements and repairs, such as pipes needed, ruts to be filled, trail to be moved, and trail widening needed.

Dave met with Jim Callahan, at the Parks office and got permission to store the nails for the toilet project in the Crow's Creek maintenance shed.  Those items were delivered and other stored items were checked.

Dave Thompson  6 hours  45 miles  (Mule, trailer, chainsaw, GPS), Evelyn Thompson  5 1/2 hours  45 miles, Sue Magierowski  5 1/2 hours  50 miles  (GPS), Ruth Franklin  4 1/2 hours  12 miles.

In addition Ruth Franklin has spent 10 hours on trail cleaning in the last couple of weeks.

 

RE: Pit toilet project at Jack Rabbit Bend

Trail log Friday, March 23, 2007 @ 10am, 1 hr, @ Jack Rabbit Bend.

Jim McClanhan of Clay Co. Parks met with Dave & Evelyn Thompson & Ruth Franklin at JRB to discuss the location of the pit toilet. It was agreed to relocate the pit toilet down the hill and out of sight of the homes across the street. The location was marked with a stake & flag. Jim stated that they’re planning on starting the project next week (after dig rite visits the site).

E&M Precast contacted Jim McClanhan regarding the shape of the risers and it’ll be up to NTG to locate & purchase toilet seats to fit.

 

We were told that Charlie Barr is once again the Director of Parks……regarding the needed concrete for the project it was suggested that we contact Charlie Barr and see if we can purchase the needed 2 yards through the parks department @ $75 per yard.

Later, Dave, Evelyn & Ruth went on to Access 15 to measure (135’x115’) to get an idea of the size the Access 22 to become (Bruce Clark stated that access 22 would be similar in size to access 15).

Upon arriving home Dave contacted Dig Rite and gave them the location & GPS reading of the pit toilet so that the utilities (if any) could be located. They said it’d be done by 3/27/07.

On March 15, 2006 volunteers met at Orscheln's in Kearney.  We rode together in Dave Thompson's truck to the home of Jim Jefferies in Lathrop, Mo. to collect building materials that Jim donated for the Jack Rabbit Bend Toilet Project.  The materials collected were hauled in Dave's 18 foot dump trailer to the Clay County Maintenance Yard in Crow's Creek Park in Smithville, Mo. and unloaded for storage.

Parks has offered to supply some of the materials that we have not been able to collect.  They have agreed to supply the T-1-11 siding and the Bronco Brown paint.

Dave Thompson and Sue Magierowski drove to E & M Precast in Trimble, Mo. where we placed an order for a 1250 gallon vault with 2 risers and one vent hole.  With a tax exemption letter the cost for the vault is $610 plus $40 for delivery and setting it in hole.  Jim Callahan will be the Clay County Parks contact for delivery date.

Dave Thompson  6 hours  100 miles, Dave Kitchen 3 hours 10 miles, Skip Fitzgerald 3 hours 10 miles, Sue Magierowski 6 hours 100 miles.

  

Login Form